The Dog River Reservoir represents years of planning and investment to ensure Douglas County is prepared for the future. As our community continues to grow, having a reliable water supply is essential for both our residents and the businesses that choose to plant their lives here.

This project has been decades in the making and reflects the long-term vision to ensure Douglas County has a safe and dependable water supply long into the future, especially during times of increasingly worse droughts in our area.

While we have to endure some growing pains as we build this project, we are excited about having it completed in 2029 and once again opening our refreshed and modernized Recreation Area to our residents and businesses to enjoy the beautiful reservoir.

Investments like this position our community for the next 50 years and beyond, allowing us to meet future demand while maintaining reliable service.

“The Dog River Reservoir is more than a water source—it’s an investment in the future of Douglas County and the quality of life for generations to come.” – Gilbert Shearouse

Dog River Reservoir Expansion - Project Phases

Dam/Spillway
PHASE A
Dam/Spillway (Construction in progress)
Constructing three new earthen dams and a new concrete spillway.

⚙️ CURRENT ACTIVITY: Currently building up the east embankment dam, excavating the new spillway and starting concrete in the stilling basin

Pump Station
PHASE B
Pump Station (Construction in progress)
Constructing a new intake pump station with three 2500HP vertical turbine pumps and a new electrical building.

⚙️CURRENT ACTIVITY: Currently finishing excavation of the pump station, intake microtunnels completed, electrical building brick facade on-going

Hwy 166 Bridge
PHASE C
Hwy 166 Bridge (Construction in progress)
Constructing a new 800' bridge adjacent to the existing bridge to accommodate the new reservoir water level

⚙️ CURRENT ACTIVITY: Currently drilling and pouring the bridge caisson foundations and constructing the new roadways

2029
Project Milestone
Construction Completion Target
Year: 2029

Latest Project Update

See the latest progress on the Dog River Reservoir Expansion Project, including ongoing construction activities and major project developments.

Project Progress

See the Reservoir Taking Shape - Gallery

Have a question? Find answers in our Frequently Asked Questions below.

About the Project

Construction

Water Level and Reservoir Size

Highway 166 and Transportation

Environmental and Regulatory Questions

Recreation and Public Access

Why the Project Matters

Project Management